Project Order Activities Duration
Pulp mill
Stendal, Germany
(Building)
Define and formulate the claims (client) and counterclaims (contractor) after finishing the work on site - Screening of the relevant correspondence
- Screening of the minutes of meetings
- Refurbishing the existing supplements
- Preparation of additional supplements
- Evaluate the value of the counterclaims
- Defining and negotiating a compromise line
6 months
Main station
Berlin, Germany
(Building)
Supply of the project team on site - Managing of the correspondence
- Participation in meetings
- Registration and cancelling of impediments (obstruction notices)
- Reacting to notices of default in time
- Contract-compliant formulating and negotiating the supplements
- Co-ordination and documentation of the measurements
10 months
Power plant
Duisburg, Germany
(plant manufacturing)
Define and formulate the claims (client) and counterclaims (contractor) after finishing the work on site - Refurbishing the existing supplements
- Preparation of additional supplements
- Evaluate the value of the counterclaims
7 months
Power plant
Grevenbroich-Neurath
(plant manufacturing)
Claim management and Contract management on site (during the complete erection phase) - Preparation of obstruction notices and notices of concerns
- Continuous comparison of the scope of performance agreed in the contract and the scope of performance realized
- Preparation and negotiation of supplements
- Managing of the correspondence relevant to the contract
36 months
Intersection Leutzscher Allee
Leipzig, Germany
(underground construction)
Preparation of supplements - comparison of scope of performance agreed in the contract to the scope of performance realized
- Contract-compliant formulating the supplements correspondent to the VOB
1 month