Overview of realized projects
| Project | Order | Activities | Duration |
| Pulp mill Stendal, Germany (Building) |
Define and formulate the claims (client) and counterclaims (contractor) after finishing the work on site |
- Screening of the relevant correspondence - Screening of the minutes of meetings - Refurbishing the existing supplements - Preparation of additional supplements - Evaluate the value of the counterclaims - Defining and negotiating a compromise line |
6 months |
| Main station Berlin, Germany (Building) |
Supply of the project team on site |
- Managing of the correspondence - Participation in meetings - Registration and cancelling of impediments (obstruction notices) - Reacting to notices of default in time - Contract-compliant formulating and negotiating the supplements - Co-ordination and documentation of the measurements |
10 months |
| Power plant Duisburg, Germany (plant manufacturing) |
Define and formulate the claims (client) and counterclaims (contractor) after finishing the work on site |
- Refurbishing the existing supplements - Preparation of additional supplements - Evaluate the value of the counterclaims |
7 months |
| Power plant Grevenbroich-Neurath (plant manufacturing) |
Claim management and Contract management on site (during the complete erection phase) |
- Preparation of obstruction notices and notices of concerns - Continuous comparison of the scope of performance agreed in the contract and the scope of performance realized - Preparation and negotiation of supplements - Managing of the correspondence relevant to the contract |
36 months |
| Intersection Leutzscher Allee Leipzig, Germany (underground construction) |
Preparation of supplements |
- comparison of scope of performance agreed in the contract to the scope of performance realized - Contract-compliant formulating the supplements correspondent to the VOB |
1 month |